How to Customize Task Dependencies in Microsoft Project

Posted on

In our last post, we demonstrated several different ways of adding a task dependency in Microsoft Project. The default when setting these links is to set up a finish-to-start dependency, so this post will cover how to establish other types of dependencies, as well as how to add lag or lead time, and finally how to determine the correct order for the tasks.

Establishing Other Types of Dependencies

If a finish-to-start task dependency does not accurately reflect the relationship between two tasks, you can use the Task Dependency dialog box to change the dependencies among your tasks. To access the Task Dependency dialog box, simply double-click the dependency link line between the tasks in the Gantt chart. (more…)

Posted in General Project Management, Microsoft Project | Tagged , , , , , , , , , ,

Return top

What Are the Different Types of Task Dependencies

Posted on

Once the WBS is built, you are ready to decide the order tasks will be performed. Some tasks depend on one or more tasks before they can start. For example, you can’t put up the walls until you pour the foundation. Some tasks need to start or finish at the same time, while other tasks can’t start until another one is already underway.

(more…)

Posted in General Project Management, Theory | Tagged , , , , , , , , , , ,